SIX BESPOKE DRILL CENTRE TEMPLATES DELIVERED TWO MONTHS EARLIER THAN CONTRACTED - Aquaterra Energy

SIX BESPOKE DRILL CENTRE TEMPLATES DELIVERED TWO MONTHS EARLIER THAN CONTRACTED

C L I E N T:

PREMIER OIL
CATCHER FIELD DEVELOPMENT

P R O D U C T:

DRILL CENTRE TEMPLATES

Premier Oil approached us to support them with their Catcher Area field development requirements in the central North Sea. Their focus was on three discoveries on Block 28/9a and 28/10c, namely the Catcher, Varadero and Burgman fields.

Aquaterra Energy delivered six Drill Centre Templates for the project two months earlier than contracted, with design and operational enhancements creating hours of rig time savings. Download to read more.